IECI signed an agreement to provide the site design and permitting services for an exciting 54 acre, 30 building, 556 multifamily complex in Greenwood, IN. Wildcat Ridge will be located just east of I65 and south of County Line Road. IECI will have several challenges including site drainage and not having done work in Johnson County for several years. IECI anticipates that the project will take 2 years to construct. In the Perry Industrial Park, IECI has two projects underway with Becknell Industrial. One Project is in Perry Industrial Park II, Section 2, and is the design and re-platting of Lots 14 and 15 at the NE corner of Perry Boulevard and S.R. 267. This site will be re-platted to one lot and prepared for a 68,000 square ft. refrigerated facility. The site design will include preparing for a possible future addition that would more than double the facility’s size. The secondary plat/development plans were submitted in May, targeting June approval.